防水聚酯网格布施工指南:从材料配比到施工技巧
材料准备与聚合物砂浆配制
Material Preparation and Polymer Mortar Mixing
1. 专人负责砂浆配制:必须由专业人员操作以确保搅拌质量。
1. Dedicated Mixing Personnel: Must be handled by professionals to ensure mixing quality.
2. 开桶搅拌:逆时针旋转打开桶盖,使用搅拌器充分搅拌粘结剂,避免分离现象。
2. Barrel Opening and Mixing: Open the barrel counterclockwise and mix the adhesive thoroughly to prevent separation.
3. 配比标准:KL粘结剂:425#硫铝酸盐水泥:砂子(18目筛)=1:1.88:3.25(重量比)。
3. Mixing Ratio: KL adhesive : 425# sulphoaluminate cement : sand (18-mesh sieve) = 1:1.88:3.25 (by weight).
施工流程关键步骤
Key Construction Steps
4. 混合搅拌:先将水泥和砂子混合,再加入粘结剂均匀搅拌,呈粥状稠度。
4. Mixing Procedure: First blend cement and sand, then add adhesive and mix thoroughly to achieve porridge-like consistency.
5. 网格布处理:按需裁剪网格布,保留搭接长度,禁止折叠踩踏。
5. Mesh Handling: Cut mesh to required size with overlap allowance, never fold or step on it.
6. 特殊部位加强:阳角处内侧做150mm加强层,门窗周边需特殊处理。
6. Reinforcement at Critical Areas: Apply 150mm reinforcement layer at inner corners, special treatment for door/window perimeters.
施工技术要点
Technical Application Points
7. 砂浆涂抹:先在EPS板面刮2mm厚砂浆,面积略大于网格布。
7. Mortar Application: Apply 2mm mortar layer on EPS board slightly larger than mesh size.
8. 网格布铺设:弯曲面贴墙,从中心向四周抹平,确保完全嵌入砂浆。
8. Mesh Installation: Place curved side against wall, smooth from center outward ensuring full embedding.
9. 搭接要求:网格布搭接≥70mm,切断部位需补网搭接。
9. Overlap Requirements: Minimum 70mm overlap, cut areas require patch overlapping.
后期处理与养护
Post-Application Care
10. 保护措施:施工后4小时防雨淋,易碰撞部位需特别防护。
10. Protection Measures: Prevent rain exposure for 4 hours, extra protection for impact-prone areas.
11. 养护标准:气温>15℃时养护≥48小时,<15℃时≥72小时。
11. Curing Standards: Minimum 48 hours curing above 15℃, 72 hours below 15℃.