昆明市出台新版建筑垃圾处置审批程序 优化营商环境
昆明信息港讯 - 为贯彻落实全省政务服务事项"五级十二同"标准要求,进一步优化提升营商环境,昆明市城市管理局近日公示了修改完善的《城市建筑垃圾处置审批程序》。
Kunming Information Port - To implement the provincial "five-level twelve-same" standard for government services and further optimize the business environment, the Kunming Urban Management Bureau recently announced the revised "Urban Construction Waste Disposal Approval Procedures".
核心审批要求:
Key Approval Requirements:
- 施工场地出口须建设洗车作业平台和防污降尘设施
- Construction sites must establish vehicle washing platforms and dust prevention facilities
- 申请材料包括:核准申请表、处理方案、消纳处置合同和运输合同
- Required documents: approval application form, disposal plan, disposal contract and transportation contract
- 许可审批时限为8个工作日
- The approval process takes 8 working days
特殊情形处理:
Special Circumstances Handling:
对于抢险救灾等紧急情况,可按照应急管理规定先行处置后报备;重大项目可"一事一议"特殊审批。
For emergencies like disaster relief, disposal can be done first with subsequent reporting; major projects may receive special case-by-case approval.
审批流程优化:
Streamlined Approval Process:
- 受理(1个工作日)
- Acceptance (1 working day)
- 勘察审核(区内2日/跨区4日)
- Inspection review (2 days for same district/4 days for cross-district)
- 审批决定(3个工作日)
- Approval decision (3 working days)
- 制证与送达(即时)
- Document issuance and delivery (immediate)
后续监管要求:
Post-approval Supervision:
许可信息需录入全市建筑垃圾运输处置综合信息管理平台,并在工程出口处公示,接受社会监督。
Approval information must be entered into the city's construction waste management platform and displayed at project exits for public supervision.
此次审批程序修改旨在通过标准化、透明化的审批流程,提高建筑垃圾处置效率,同时加强环境保护要求,推动昆明市建筑行业绿色发展。
The revised procedures aim to improve construction waste disposal efficiency through standardized, transparent approval processes while enhancing environmental protection requirements to promote green development in Kunming's construction industry.